Brief Description Of Works
Refurbishment of the Arts One Lecture Theatre at Queen Mary University of London. This included new speaker, AV system, lecture theatre seating, flooring and redecoration. Works were carried out during the summer holiday period when no students were on site but various contractors were working in various areas throughout the campus.
Key Points
Communication between contractors was a key success factor at completing the works within programme.
Perfect organisation and scheduling for each phase of works meant that we were able to meet the shortened programme set by the QMUL project team.
Flexibility of our operatives and sub-contractors working out of normal hours to ensure each stage was complete at the correct time in the programme.
Client
Queen Mary University of London
Project
Internal Refurbishment
Duration & Completion
3 weeks / September 2017
Contract Value
£35,000
Key Role
Principal Contractor